Where: The install site was at the CEGEP de l’Outaouais which is the largest public college in the Outaouais region.
Why: The CEGEP’s old Carrier unit was on borrowed time. The unit was decommissioned by Seguin Morris and sold for scrap metal.
Who: Mécanique MAP which is a mechanical contractor acted as the general contractor as well on this project.
What: HTS sold 2 magnetic bearing chillers to replace one large Carrier centrifugal chiller. We sold one, 200-ton WMC as well as one, 500-ton WME. This was the first WME in the Ottawa Gatineau region! This WME also had to be brought in the mechanical room in pieces due to the existing constraints of the mechanical room. This was done with the help of our local Daikin Service branch.
How: With the help of group 22RW, BPA specified the very first WME chiller in our region.