Arise Medical Center is a local Austin physician-owned and operated hospital. This 47,000 square-foot facility needed to replace an aging chiller with a more efficient option.
HTS was chosen for the project based on both pricing and our offering of high-efficiency products. The current chiller was not meeting the cooling demands of the hospital, so HTS was tasked with finding a solution that could effectively cool the space while adding value to the building and reducing energy costs.
As the center performs several surgeries, they could not afford to have any downtime for installation. So over one weekend, a 265-ton Daikin Pathfinder Air Cooled Screw Chiller was delivered and started-up at the facility. This chiller proved to be the best-priced option for the hospital and is now earning the owner an Austin Energy chiller rebate along with decreasing energy costs by 30%.